On December 11, 2016, the first unit of the Master Sunjialou 49.4MW project of Yanchi Wind Farm was officially connected to the grid for power generation. Prior to this, the first line of the second phase of the 35KV collector line Wangma has also been successfully transmitted. This move marks that the Master Sunjialou Wind Power Project has been officially connected to the State Grid. The project construction team will continue to work hard and strive to complete the entire grid connection as soon as possible.