In order to further improve the health level of wind farm equipment and ensure the safe and stable operation of wind farms, from August 8, 2017 to On August 14th, during the power outage period during the power grid reconstruction and expansion, the comprehensive maintenance of the substation of Yanzhou No. 1 Wind Farm was carried out as soon as possible. There are more than 40 maintenance and test projects in total.
In this comprehensive overhaul task, all employees in the station voluntarily gave up rest time and worked overtime to complete various task indicators . After the day's work is over, all the staff will organize themselves to look over the drawings and technical manuals for various difficult problems encountered in the day's work to find out the reasons and determine the solutions in detail. With the joint efforts of the company's leaders and all inspection personnel, it was successfully completed. this comprehensive inspection task.